Monday 15 August 2011

WEEK THREE

During this week  we started the sketch of our floor plan trying our best to use the scale rule to effect in our drawings we were able to label and name all the sub floor parts such as PILES, FLOOR BEARING, FLOOR JOISTS, and with these part we were told to measure the needed quantity and set a price for each of the certain types of timber required such as 

4xBEARINGS(H3.2 treatment)

2 BEARINGS @5.700m
2 BEARINGS @4.320m
 
7xBARRIER JOISTS (H1.2 treatment)
2 REAR JOISTS @5.700m
4 SIDE JOISTS @3.100m
1 FRONT JOIST @4.320m

10xJOISTS @2.065m(H1.2 treatment)

10xNOGS @.387m


our tools were also distributed out to us and all our stationary  which included

TOOLS:
1xHAMMER
1xRULER
1xMEASURING TAPE
1xCOMBINATION SQUARE
1xHANDSAW
1x19mm CHISEL
1x32mmCHISEL
1xBUILDERS PENCIL

STATIONARY:
1xRED PEN
1xBLUE PEN
1xBLACK PEN
1x2H PENCIL
1x EL-531WH CALCULATOR
1xSKETCH PAD
1xFOLDER
1xRULER

and to end off week three we spent the whole day in the work shop perfecting our joint exercises which consisted of the CORNER HALVING, STOPPED TEE HALVING, SINGLE DOVE TAIL HALVING AND THE DOVE TAIL HALVING how ever we did not get to attempt the dove tail halving due to the time we also learnt to cut the angle of the single dove tail halving which i thought would prove to be a challenge  but a steady hand and a-lot of concentration proved the job to become a simple task  

No comments:

Post a Comment