Saturday 25 February 2012

week two 2012

in this week we continued with the profiles and completed them before the day subsided after the profiles were done we began to clean  the covered area and continued to clear this area up to satisfaction our tools were handed out to us excluding the drill set we were given a sketching exercise and started our site set out  and wer given the opportunity to start the site plan and  a critical path planning scheme for the house was drawn up and added to with the input of unit standards and when they had to be completed and also dates in which the path had to abide by the rest of the week consisted of completing the critical path plan to satisfaction and we wer given a plan for the house we were to be constructing

No comments:

Post a Comment